Questions on Project Communication Management
- The process of Manage Stakeholders Expectations is part of which process group?
- Planning
- Monitoring and Control
- Executing
- Initiating
- The project you are managing has nine stakeholders. How many channel of communications are there between these stakeholders?
- 9
- 8
- 45
- 36
- Which of the following is not an example of formal communication?
- Contract
- email
- Project status report
- Status meeting
- Which of the following process is not included in project communication knowledge area?
- Documenting Project Closure
- Plam Communications
- Distribute Information
- Managing Stakeholder Expectations
Answers
- c. Manage Stakeholder Expectations is part of executing process group.
- d. There will be (9*8)/2 channel of communication.
- b. Communication via email is not considered a formal communication.
- a. Document Project Closure is not a process in Project communication knowledge area.