Questions on Project Risk Management
- Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called?
- Risk Management Plan.
- List of risks.
- Monte Carlo diagram.
- Risk Breakdown Structure.
- Which of the following statements is true about risks?
- When evaluating risks their impact should be considered, however probability of occurrence is not important.
- Risks if they happen always have negative impact and not positive.
- Risk register documents all the risks in detail.
- Risk response plan is another name for Risk Management Plan.
- Beta is the Project Manager of a Road construction project. During a project review, Beta realizes that one particular risk has occured. To take appropriate action against risk that has happened, Beta needs to refer to which document?
- Risk response plan
- Risk management plan
- Risk breakdown structure
- Risk register
- During which stage of Risk planning are risks prioritized based on probability and impact?
- Identify Risks
- Plan Risk responses
- Perform Qualitative risk analysis
- Perform Quantitative risk analysis
- During which stage of Risk planning are modeling techniques used to determine overall effects of risks on project objectives for high probability, high impact risks?
- Identify Risks
- Plan Risk responses
- Perform Qualitative risk analysis
- Perform Quantitative risk analysis
- Andrew is a Project Manager for Green Valley project. A risk management plan has been prepared for the project. Which of the following should Andrew do next?
- Perform Qualitative risk analysis
- Perform Quantitative risk analysis
- Identify Risks
- Plan Risk responses
- Which of the following processes has risk register as the primary output?
- Plan Risk Management
- Identify Risks
- Monitoring and Control Risks
- Perform Qualitative Risk Analysis
- Five of the processes in Project Risk Management are from which process group?
- Initiating
- Planning
- Executing
- Monitoring and Control
- John Strauss is a Project Manager for a reforestation project. To identify the risks involved, John sends a questionnaire to gather inputs from experts. Which technique is John using?
- Delphi technique
- Interviews
- Brain storming
- Documentation review
- Mathew is a Project Manager for software migration at a bank. A major risk that has been identified is attrition of resources. As a strategy to respond to this risk, Mathew, with support from Senior Management, provides good increments to his team members. What type of risk response is Mathew following?
- Accept
- Avoid
- Transfer
- Mitigate
- Which of these is a valid response to positive risks?
- Exploit
- Mitigate
- Enhance
- Share
Answers
- d. Hierarchical description of risks is called Risk Breakdown structure.
- c. Risk register documents the risks in detail.
- a. Beta needs to refer to the Risk response plan that documents responses to identified risks.
- c. Risk probability and impact are defined during Qualitative risk analysis.
- d.
- c. Risk identification is performed after performing the risk management plan.
- b. Process of Identify Risks has Risk register as the major output.
- b. Five of the six processes in Project Risk Management are part of the Planning process group.
- a. John is using the Delphi technique to identify risks.
- d. Mathew is mitigating the risk by reducing the probability of risk happening
- Risk mitigation is a response to negative risks and not positive risks. Positive risks may be responded by - "Exploit", "Enhance", "Share", "Accept".